Nov 19- A nice article in the Minneapolis Star Tribune today about Granite House. Here's a link to the story online: 
http://www.startribune.com/metro-area-couple-build-haven…/…/

Nov 15- November 16 is GIVE TO THE MAX DAY and Granite House is an approved charity. Please think of us as you do your annual giving. Every donation, no matter how small, will put our name into the running for an hourly prize drawing. The Granite House site is 
https://givemn.org/organiz…/granite-house-inc-20151015100331

Our Home and Garden Event was last night and it was great fun. Our guests saw a slide show about the construction progress and saw the amazing plans for our community accessible sensory garden. They signed up to sponsor trees, shrubs, and garden elements and also to volunteer to dig in the dirt next summer. Watch for more information about this exciting adventure.

UPDATES FROM OUR FACEBOOK PAGE for 2017: July-Dec

Oct 12- More house photos coming soon, but here are some great shots of our Granite House team at the Sept 23 Walk for Thought at Long Lake Regional Park. This annual event is sponsored by the MN Brain Injury Alliance and we have had a team there for four years. A fun outing for Aaron's caregivers and their families, plus board members, friends and neighbors.

Sept 30- Windows are in and the metal roof panels are being installed this week. We are effectively "dried in." The rough grading around the main entrance is settling and will have a concrete stoop and patio poured, so that wheelchairs can be taken in and out without a ramp.

Sept 12- Raising the roof! The house is taking shape with the roof trusses complete and roof sheathing beginning. The screened porch is in the photo on the far left. The grading will bring the soil right up close to the entry door and then the concrete porch will be poured.

Nov 30- The siding is almost finished at the house. We love the bold red color with the bronze metal roof. The siding is pre-painted and finished, and has a guarantee. The roof will last for generations.

Granite House

Granite House

Nov 1- Granite House will be hosting a vendor table this Saturday at the Fall Consumer and Family Conference for the Minnesota Brain Injury Alliance. Come and learn about brain injury and support those with a severe and permanent diagnosis by stopping at our table. Here's the link to the Conference, which is held in Roseville at the the New Life Presbyterian Church from 1-4 pm.   https://www.braininjurymn.org/events/famconf.php

Oct 30-The roof is done! Metal fabricating by Architectural Construction Services Inc and installed by Metro Panel at a charitable discount. Excellent product, installation, and results. This roof will last for generations!

Granite House

Granite House

For more photos of the building progress, go to our BUILDING SITE tab on the website. 

Sept 21- The triple-glazed Loewen windows were installed this week. Such great quality at a generously discounted price! The manufacturers in Canada as well as the distributors, Synergy Products, gave us discounts. When the framers were installing them, they were so sound-proof that they could hardly hear each other from the inside to the exterior. This house will be warm and cozy and cool in the summer--plus very quiet.Thank you to Loewen and Synergy!